Rained out

Paving company asks for deadline reprieve due to weather

The Pine Haven Town Council met for a special meeting last Wednesday afternoon to accept a two-week stay of work from Sacrison Paving to allow the ground to dry from the repeated showers that have prevailed this summer.

For the last month and a half, Sacrison has been repairing damage to the paved streets of Pendleton, Lakeview and Vista Grande Drives as well as raising the depth of the paving material another two inches to provide a more sustainable hard top. However, due to the unusually high rainfall this summer, the 35 day completion schedule is suffering as Wednesday made 37 days and t...