Moorcroft construction projects update

2018 Sanitary Sewer Main Replacement

This project included replacement of the sanitary sewer main in the alley between Powder River Avenue and Cheyenne Avenue from Weston Street to Park Street.

Sanitary sewer installation has been completed and Falcon Construction is currently working to replace concrete pavement on Campbell, Crook, Weston and Goshen Streets. Streets in this area will be closed for periods of time as needed for replacement of pavement. Once concrete is cured, gravel will be placed in the alleys.

Temporary aggregate base surfacing will be used on Park and Goshen Streets; this is being done since pavement will be removed and replaced on those streets during Phase I of the Powder River Water Main Replacement project that will take place early next year.

There has been some interest by landowners to replace the remainder of their service line from the property line to their house. Hot Iron is willing to provide quotes to interested landowners for service line replacement. Bryan Garland with Hot Iron may be reached at 307-682-8702.

The project is anticipated to be substantially complete by early November with final completion taking place prior to Thanksgiving.

 
 