Picking up the pace

 

March 4, 2021

RCS completed the concrete pouring for the inverts on the inside walls on both the east and west contact chambers of the lagoon on Monday and are nearing completion for the rip rap install around lagoon cell two as well as having removed the rip rap around the smaller lagoon cell three. Excavation and concrete formwork for the new chlorination building also began this week.

...



For access to this article please sign in or subscribe.

 
 

Powered by ROAR Online Publication Software from Lions Light Corporation
© Copyright 2023